Checking a builder, a guide by Dotto
Notice to home ownersBefore you hire

Check a local builder before you sign

A guide to choosing and checking a builder for home building work in Australia, published by Dotto from the official sources linked on each page. Six short notices cover the licence, the warranty insurance, the deposit, the contract, changes to the work, and what happens when something is wrong.

Licence no.
Check it here
Warranty insurance
Check the certificate
Deposit
Check the cap
Contract
Check what it must say
The sign on the fence

A name and a number are where checking starts

In Queensland, the QBCC notes that on large jobs where the contractor controls the site, such as new builds, licensed contractors will display a sign with their contact details. When they advertise, licensed contractors there must give their contractor name, matching the name on the licence, and their QBCC licence number.

A name and a number on a sign, an ad or a quote are only the start. Victoria’s Building and Plumbing Commission puts it plainly: an ad, a business card, a quote or someone’s word is not enough on its own, so check a builder’s details before signing a contract or allowing work to start.

This guide covers home building work in general: building a home, extending it or renovating it. Each notice says which state a rule comes from, because the rules are set state by state.

Licence no.

Where to check a builder’s licence

Each register below is kept by that state or territory’s government. Look the builder up yourself, by name or licence number, rather than relying on a printed number alone.

A selection of seven states and territories, each taken from that government’s own page, read 8 October 2026. Notice 01 says what each record shows.
State or territoryWho keeps itWhere to look
New South WalesNSW Government (Verify NSW)Check a licence on Verify NSW
VictoriaBuilding and Plumbing Commission (BPC)Find and check a practitioner
QueenslandQueensland Building and Construction Commission (QBCC)QBCC licensee register
Western AustraliaBuilding and EnergyFind a registered building service provider
South AustraliaConsumer and Business Services (CBS)Find a licence holder
TasmaniaBuilding Standards TasmaniaFind a licensed tradesperson
Australian Capital TerritoryAccess CanberraBuilding and construction, then “List of builders”

The six notices

Four numbers

Four numbers to know, in three states

The thresholds that decide when you need a written contract and warranty insurance, how much deposit a builder may ask for, and how long you have to change your mind.

Read on each regulator’s page on 8 October 2026. Every figure comes with conditions, which the notices set out.
The ruleNSWVictoriaQueensland
Written contract neededOver $5,000 including GST A major domestic building contract for work involving more than one trade and worth more than $10,000 Work valued at more than $3,300
Largest deposit10% 10% under $20,000; 5% at $20,000 or more (changing by 1 December 2026; see the note below) 20% at $3,300 or less; 10% from $3,301 to $19,999; 5% for $20,000 or more (Level 2)
Warranty insurance requiredMost residential building work over $20,000 Eligible work over $20,000, under contracts signed on or after 1 July 2026 Residential construction work over $3,300
Cooling-offFive clear business days, for contracts over $20,000 Five days to change your mind after signing, which Consumer Affairs Victoria says you no longer have if you get independent legal advice before you sign Generally five business days, for contracts over $3,300
Victoria: law changing

Victoria passed new building contract laws in September 2025 that take effect by 1 December 2026 and may change the Victorian deposit limits, payment stages and contract rules in this table. Until then, Consumer Affairs Victoria says the current laws remain the same. Check Consumer Affairs Victoria before you sign.

In order

From the first quote to the last payment

  1. Before you choose

    Look the builder up on your state’s register. In Victoria, the BPC’s search shows whether a registration or licence is current, what type of work it allows and whether it has any conditions or limits. Notice 01

  2. Before you sign

    Read the whole contract. In NSW, builders must give you the Consumer Building Guide before a contract for residential building work over $5,000. Notice 04

  3. Before you pay a deposit

    See the insurance certificate. NSW’s advice is not to pay the deposit until you have seen your contractor’s insurance certificate and checked it is valid; Consumer Affairs Victoria says to hold the deposit back until the builder hands you a certificate of currency for your property. Notice 02 and notice 03

  4. While the work goes on

    NSW’s advice is that progress payments should match work actually done, not time on the job. In Queensland, a contractor must give you a variation in writing before the variation work starts, unless it is urgent and that is not reasonably practicable. Notice 05

  5. After the work is finished

    In NSW, statutory warranties last six years for major defects and two years for all other defects, from the date the work was completed. Other states set their own periods. Notice 06